Work Done in 2015

The Steering Committee authorized and completed the following studies:

  • Planning Study on bylaws, development rules and proposed changes by the City and the impact of these on development options;
  • Geotechnical study of the soil conditions with respect to environmental regulations, load bearing capacity, etc.;
  • The first formal survey of the two sites owned by Trinity (we think of our site as one, but on the City rolls, the parking lot is a separate site to the church building site);
  • Environmental Site Assessment I and II.